Lots of work done over the past day or two - we had dug the trench for the fence footing when the local construction crew told us it was not deep enough. We had cut down through the top soil (~12-16") and reached clay, but they said the frost point was ~60-80cm. Hence, we did more digging. We took the whole trench down to 60cm, then every two meters dropped a hole down to 80cm. We also got a good section of the rebar in for the footing. in